Service Milestones for Wide Area Network (WAN) Services
In my opinion, it seems like carriers have gone backwards in
WAN installations and it has become more cumbersome in spite of the technology
available. Part of the problem, again, in my opinion, is that proper
expectations are not established upfront by the Sales team to the end-user. The
reality, is most carrier Account Teams are not aware of the process as they
should nor do they fully understand the sequence of events.
Based on a recent experience installing a WAN and IP
Services, I thought it might be beneficial to post the actual Service Provider
Milestones and Descriptions. This include:
Order Creator:
The order is submitted once the contracts are signed by the customer and
the sales team. The sales team sends the order to the Front End Ordering team.
The order is then handled by a Customer Service Specialist (CSS)/FEO. The CSS
team member then writes the initial order on the MDS form.
Firm Order Delivery (FOD): The Assembler
generates this date and the date helps to confirm customer's order(s) and
service requests internally. The Assembler sends Access Service Request (ASR)
to the Local Exchange Carrier (LEC) if the LEC confirms acceptance, FOD Date is
posted and a PON is generated.
Purchase Order Number (PON): Once the LEC
acknowledges the order a PON Is sent back to the Service Provider.
Universal Service Order (USO): Once the order
has been submitted to the Order Manager by the Order creator, the information
will be verified by the OM and then the order is released. This process generates the USO. The USO number is used to track updates and
status for each location. You can use
SOTS, EFMS or IOS.
Firm Order Confirmation (FOC): This milestone
is met after the site survey has been completed by the Engineer who generates a
letter to the customer highlighting customer’s site requirements if
applicable. Internally, the LEC (Local
Exchange Carrier) issues key pillars or milestone dates including service delivery
dates. If the site is within the Service Provider footprint FOC’s due date is
approximately 16 days after FOD. If it
is outside the Service Provider footprint, it is approximately 22 days.
*If this date is missed the PM is responsible for initiating escalation.
*If this date is missed the PM is responsible for initiating escalation.
Design Verified and Assigned (DVA): End to end facility design and verified (For
internal design team only)
Wired &Office Tested (WOT): End to end facility design wired and tested
(For internal design team only)
Record Issue Date (RID): End to end facility design complete (For
internal design team only)
(EAD)Access Circuit
Installation: This service milestone
takes place after FOD , FOC and the internal infrastructure is completed. The circuit is installed at customer’s site
by the Local Exchange Technician
*If EAD is missed, the PM is responsible for initiating and following up with the escalation process.
*If EAD is missed, the PM is responsible for initiating and following up with the escalation process.
(CTA) Circuit Tested
Available: This is a test
conducted to confirm the success of the circuit installation after the Service
Provider has supplied equipment to the data circuits and routers.
*If CTA is missed, the PM is responsible for initiating and following up with the escalation process
*If CTA is missed, the PM is responsible for initiating and following up with the escalation process
Pretest:
A technician goes out to the customer site and test the circuit. This is
primarily done for IPFLEX orders
Porting: Number porting is the handoff of
a phone number from one carrier to another at the request of a customer. (If
Applicable). The porting is scheduled by
the Order Manager
Test and Turn Up (TTU): Once the router installation has been tested, the Service Provider will
prepare to perform the Test and Turn-up of the Service on the Scheduled Due
Date and Time. During this process a
technician will only be dispatched to go to the customer premises to assist
with this process if the customer paid for onsite install, which is an extra
charge. If the customer selected Tele install then the customer is responsible
for connecting the smart jack to the router.
* The Order Manager will
contact the customer during this process in order to verify all information and
to go into details regarding the necessary steps and or requirements to be met
by the customer before the TTU date.
Due Date: This date represents the day that the Service
Provider guarantees to be completed. (*if date is missed, reach out to your
OM) It also starts the billing
process. If the DD comes and the
customer is not ready (CNR) the billing still starts. (Reach out to AM to
inform them of the situation)
*Due Date will be changed if any Risks or Delays comes up that will affect milestone dates
*Due Date will be changed if any Risks or Delays comes up that will affect milestone dates
*Escalation process
1)
Generate an email
to the Order Manager and if applicable
any online tools/portals
2)
If no response
within 48 hours raise it to the OM’s Manager and copy your AM
3)
If still no
response within 24 hours go to your AM who will raise it to the Director’s Leve